What an energisation readiness review checks, 30 days out.

Kestrel Power plans to run a formal readiness review 30 days before every energisation. It is the gate between commissioning and handover in our delivery model, and the named commissioning lead signs it.
The review does not replace energisation approval, which the network service provider owns. It tests whether we are ready to receive it: whether the plant, protection, records and people exist and agree with each other.
What the review checks
Pre-commissioning and primary and secondary injection test records complete and reconciled to the design. Network settings implemented and tested. SCADA and RTU points proven end to end, with IEC 61850 where it applies. Earth grid verified against ENA EG-1. Outstanding network approvals and the switching program agreed.
Readiness is a document trail, not a feeling on site.
Kestrel Power · Commissioning principle
Anything still open at the review is either closed, or carried with an owner, a due date and its effect on the energisation date written down.
What follows the review
Handover covers as-builts, test records and settings files, with 30 days of post-energisation support. This is how we plan to operate; we have not yet delivered it on a live project.
A review that cannot fail is not a review.
Kestrel Power · Commissioning principle
Each review will be recorded against the weekly float report for that project.